← All Georgia projects
permittingIndustrial

Project Azalea Data Center

Thomson, McDuffie County, Georgia

Estimated value
$1B
Square footage
Opened / announced
Mar 18, 2026
Owner
Project Turbo LLC
General contractor
Architect
Brands mentioned
None in public seed

Project overview

200-acre, six-building data center campus approved March 2026 near Augusta. ~400MW Jefferson Energy supply; completion target 2029 pending power upgrades.

Key specs

  • Six data center buildings
  • 200 acres
  • 400MW energy load
  • Own substation and backup generation

Still open for manufacturers

Approved — design and MEP specs forming ahead of construction.

Manufacturer watch list

  • switchgear
  • generators
  • cooling systems
  • fire suppression
  • security systems
  • raised floor