- Estimated value
- Undisclosed
- Square footage
- 342,409 SF
- Opened / announced
- Feb 1, 2026
- Owner
- CyrusOne
- General contractor
- —
- Architect
- JHET Architects
- Brands mentioned
- CyrusOne, Calpine
Project overview
Two new hyperscale data center buildings (249,090 SF + 93,319 SF with office) at Whitney campus. Construction from Feb 2026; completion July 2027.
Key specs
- DFW17B: 249,090 SF
- DFW17C: 93,319 SF + office
- 210MW power expansion with Calpine
Still open for manufacturers
Permitting/early build — MEP and tenant fit-out specs.
Manufacturer watch list
- switchgear
- cooling
- electrical
- precast envelope