← All projects
permittingData Center

Amazon / Birchwood King George Data Center Park

King George, King George County, Virginia

Estimated value
Undisclosed
Square footage
7,500,000 SF
Opened / announced
Jun 15, 2026
Owner
Birchwood Power Partners / Amazon
General contractor
Architect
Brands mentioned
Amazon, Birchwood Power Partners

Project overview

7.5 million SF data center campus proposed in King George County with Amazon as the end user. Initial phases include up to eight buildings (4M SF) and substations. Recommended for approval June 2026.

Key specs

  • 7.5M total SF planned
  • Initial 4M SF across 8 buildings
  • 2+ electrical substations
  • 15-year buildout timeline

Still open for manufacturers

Planning & zoning — future MEP and shell specs.

Manufacturer watch list

  • switchgear
  • cooling
  • substations
  • structural steel

Sources