← All projects
under constructionData Center

Related Digital / CoreWeave Data Center Campus

Cheyenne, Laramie County, Wyoming

Estimated value
$1.2B
Square footage
184,000 SF
Opened / announced
Jul 15, 2026
Owner
Related Digital / CoreWeave
General contractor
Clayco
Architect
Brands mentioned
Related Digital, CoreWeave, Clayco, Black Hills Energy

Project overview

Related Digital broke ground July 2026 on a $1.2B, 302 MW campus in Cheyenne Business Parkway. First phase is a 184,000 SF building fully leased to CoreWeave delivering 88 MW, GC Clayco, completion late 2026.

Key specs

  • $1.2B investment
  • 302 MW campus capacity
  • Phase 1: 184,000 SF / 88 MW
  • Clayco GC, leased to CoreWeave

Still open for manufacturers

Under construction — shell completion late 2026, MEP & liquid cooling fit-out.

Manufacturer watch list

  • switchgear
  • liquid cooling
  • generators
  • electrical distribution
  • precast concrete

Sources